CONTRACT NO: HY/2019/14
New Wang Tong River Bridge
Under Environmental Permit no. EP-555/2018/A
Quarterly Environmental Monitoring & Audit
Report
april - june 2022
|
CLIENTS: |
|
Highways Department |
Lam Environmental Services Limited 19/F Remex Centre, 42 Wong Chuk Hang Road, Hong Kong Telephone:
(852) 2882-3939 Facsimile:
(852) 2882-3331 E-mail:
info@lamenviro.com Website:
http://www.lamenviro.com |
|
|
|
|
|
Certified
by: |
|
________________________________ Raymond Dai Environmental
Team Leader |
|
DATE: |
|
June 2022 |
|
|
1.1.......... Scope of the Report
1.2.......... Structure of the Report
2.2.......... Project Organization and Contact Personnel
2.3.......... Construction Activities
3 Status
of Regulatory Compliance
3.1.......... Status of Environmental Licensing and
Permitting under the Project
3.2.......... Status of Submission under the EP-555/2018/A
3.3.......... Status of Submission under the EP-555/2018/A
4.1.......... Noise Monitoring
4.3.......... Water Quality Monitoring
5.1.......... Noise Monitoring Results
5.2.......... Air Monitoring Results
5.3.......... Water Quality Monitoring Results
5.4.......... Waste Management
6.1.......... Noise
Monitoring.
6.2.......... Air Quality Monitoring
6.3.......... Water Quality Monitoring
6.4.......... Summary
of Exceedance
6.5.......... Environmental Site Audit
6.6.......... Review of the Reasons for and the
Implications of Non-compliance
6.7.......... Summary of action taken in the event of and
follow-up on non-compliance
7 Complaints,
Notification of Summons and Prosecution
lIST OF TABLES
Table 2.2 Contact Details of Key Personnel
Table 3.2 Summary
of submission status under EP-555/2018/A
Table 4.1 Noise
Monitoring Station
Table 4.3 Action
and Limit Level for Noise Monitoring
Table 4.4 Air
Monitoring Station
Table 4.6 Action
and Limit Level for Air Quality Monitoring
Table 4.7 Marine
Water Quality Stations for Water Quality Monitoring
Table 4.9 Action
and Limit Level for Water Quality Monitoring
Table 5.1 Summary
of Quantities of Inert C&D Materials
Table 5.2 Summary
of Quantities of C&D Wastes
Table 8.1 Cumulative
Statistics on Complaints
Table 8.2 Cumulative
Statistics on Successful Prosecutions
lIST OF FIGUREs
Figure 2.2 Project Organization Chart
Figure 4.1 Locations
of Noise Monitoring Station
Figure 4.2 Locations
of Air Quality Monitoring Stations
Figure 4.3 Locations
of Water Quality Monitoring Stations
lIST OF APPENDIces
Appendix 3.1 Implementation Schedule
Appendix
4.1 Action and Limit Level
Appendix 4.3 Wind data extracted fro HKO Automatic
Weather Station
Appendix 5.2 Noise Monitoring Results and Graphical
Presentations
Appendix 5.3 Air Quality Monitoring Results and Graphical
Presentations
Appendix 5.4 Water Quality Monitoring Results and
Graphical Presentations
Appendix
6.1 Event and Action Plans
Appendix 6.2 Summary for Notification of Exceedance
EXECUTIVE SUMMARY
i.
This
is the Environmental Monitoring and Audit (EM&A) Quarterly Report
– April
2022 to June 2022 of New Wang Tong River Bridge under Environmental
Permit no. EP-555/2018/A (Hereafter as “the Project”). The construction works
of the Project was commenced on 12 July 2021 and the tentative completion date
is Q3 2024. This is the 4th
Quarter EM&A
report presenting the environmental monitoring findings and information
recorded during the period of 01 April 2022 to 30 June 2022.
ii.
In
the reporting month, the principal work activities conducted are as follow:
April 2022 |
May 2022 |
June 2022 |
·
Cofferdam construction ·
Construction site mobilization ·
Preliminary pilling |
·
Cofferdam construction of MP1 ·
Construction site mobilization ·
Piling construction |
·
Cofferdam construction of MP1 ·
Construction site mobilization ·
Piling construction |
Air Quality
Monitoring
iii.
1-hour and 24-hour Total
Suspended Particulates (TSP) monitoring was conducted at two monitoring station. 24-hour TSP shall be
sampled at least once in every 6 days, while sampling for 1-hour TSP shall be
at least 3 times in every 6 day in the reporting period.
iv.
No action or limit level exceedance was recorded in this reporting
period.
Noise Monitoring
v.
Noise monitoring was conducted at one noise monitoring station once per
week in the reporting period.
vi.
No action or limit level exceedance was recorded in this reporting
period.
Water Quality Monitoring
vii.
Water quality
monitoring was conducted at seven monitoring stations three days per week in
the reporting period since 17th March. However, due to no marine-based construction works before 27th May 2022, water quality
monitoring results before 27th May 2022 were taken as reference such that no
action and limit level exceedance was concluded and recorded before the day.
Review of action or limit level exceedance was conducted for water quality
monitoring results after 27th May 2022 when marine-based construction work
commenced.
viii.
Owing to accessibility and safety issues, water quality monitoring at
Station W3 was cancelled with verification from the IEC in November 2020 and
approval from the EPD in December 2020.
ix.
No action or limit level exceedance was recorded in this reporting
period as water quality monitoring results were taken as reference such that no
action and limit level was concluded and recorded. Review of action or limit
level will be conducted for water quality monitoring results when marine-based
construction work occurred.
Site Inspections and Audit
x.
During
the reporting period, the Environmental Team (ET) conducted weekly site inspections and monthly
landscape site inspections and IEC attended the joint site inspection monthly.
xi.
No
non-compliance was found during the site inspection while reminders on
environmental measures were recommended.
Complaints,
Notifications of Summons and Successful Prosecutions
xii.
No environmental complaint, notification of summons
and successful prosecution regarding the construction works was recorded in the
reporting period.
Reporting
Changes
xiii.
There are no particular reporting changes.
1.1.1.
Lam Environmental Services Limited (LES) has been appointed to work as
the Environmental Team (ET) under Environmental Permit (EP) no. EP-555/2018/A
to implement the Environmental Monitoring and Audit (EM&A) programme as
stipulated in the EM&A Manual of the approved Environmental Impact
Assessment (EIA) Report for New Wang Tong River Bridge (Register No.: AEIAR-199/2016).
1.1.2.
According to Section 10.6 of the Project EM&A Manual, the Quarterly
EM&A Report should be submitted.
Section 1 Introduction – details the scope and structure of the report.
Section 2 Project
Background – summarizes background and
scope of the project, site description, project organization and contact
details of key personnel during the reporting period.
Section 3 Status of Regulatory Compliance – summarizes the status of valid Environmental Permits /
Licenses during the reporting period.
Section 4 Monitoring
Requirements – summarizes all monitoring
parameters, monitoring criteria and respective event and action plan.
Section 5 Monitoring
Results – summarizes the monitoring
results obtained in the reporting period.
Section 6 Compliance Audit – summarizes
the auditing of monitoring results, all exceedances environmental
parameters.
Section 7 Environmental Site Audit – summarizes the findings of weekly site inspections
undertaken within the reporting period, with a review of any relevant follow-up actions within the reporting period.
Section 8 Complaints,
Notification of summons and Prosecution – summarizes the cumulative statistics on complaints, notification of summons and
prosecution
Section 9 Conclusion
2.1.1.
Silver Mine Bay is a popular bathing beach in Mui Wo, Lantau that attracted
4,550 visitors on a peak day and over 69,000 visitors utilized the beach in
2012.
2.1.2.
In order to relieve the overcrowding problem and the road safety concern
of Wang Tong Bridge (hereafter called “Old Bridge”), two bridges (pedestrian
bridge and cycle bridge) are proposed to replace the Old Bridge. The new
pedestrian bridge and the new cycle bridge (hereafter called “New Bridge”) are
also designed to align with the future amenity development on the northern side
of the Old Bridge. The location of the project site is shown in Figure 2.1.
2.1.3.
The Project consists of a designated project under Part I, Schedule 2 of
the Environmental Impact Assessment Ordinance (EIAO) which is Item C.12 – (a)…a
dredging operation which is less than 500m from the nearest boundary of an
existing…(iii) bathing beach…
2.1.4.
The major components of the Project under Environmental Permit (EP) (EP
No. EP-555/2018/A) comprises: (i) demolition of the existing Wang Tong River
Bridge; and (ii) construction of a new twin bridge with segregation for
pedestrians and cyclists.
2.2.1
Highways Department is the overall project controllers for the Project.
For the construction phase of the Project, Contractor(s), Environmental Team
and Independent Environmental Checker are appointed to manage and control
environmental issues.
2.2.2
The project organization and lines of communication with respect to
environmental protection works are shown in Figure 2.2. Key personnel and contact
particulars are summarized in Table 2.2:
Table 2.2 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
Highways
Department (HyD) |
The Engineer for the
Contract |
Senior
Engineer |
Mr. Terry Chung |
3903 6799 |
3188 3418 |
Engineer’s
Representative |
Engineer |
Mr. Yeung Sui Chung |
3903 6813 |
3188 3418 |
|
Unison
Construction Engineering Limited |
Contractor
|
Site
Agent |
Mr. Peter Lui |
2690 2232 |
2363 3199 |
Environmental
Officer |
Ms. Suki Chan |
||||
Independent Environmental
Checker (IEC) |
Independent Environmental Checker (IEC) |
Mr. James Choi |
|||
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.3.1 In the reporting period, the
principal work activities conducted are as follows.
April 2022 |
May 2022 |
June 2022 |
·
Cofferdam construction ·
Construction site mobilization ·
Preliminary pilling |
·
Cofferdam construction of MP1 ·
Construction site mobilization ·
Piling construction |
·
Cofferdam construction of MP1 ·
Construction site mobilization ·
Piling construction |
2.3.2 Overall layout showing work areas
is shown in Figure 2.1.
3.1.1.
A summary of the current status on licences and/or permits on
environmental protection pertinent to the Project is shown in Table 3.1.
Table 3.1 Summary of the
current status on licences and/or permits on environmental protection pertinent
to the Project
Permits and/or
Licences |
Permit. No. / Account
No. |
Valid From |
Expiry Date |
Status |
|||
Notification pursuant
to Air Pollution Control (Construction Dust) Regulation |
Form NA submitted to
EPD on 25 June 2021. |
||||||
Environmental Permit |
EP-555/2018/A |
16 Dec 2020 |
N/A |
Valid |
|||
Billing Account for Disposal of Construction Waste |
7038550 |
29 Mar 2021 |
End of the Project |
Valid |
|||
Registration as a Chemical Waste Producer |
5213-962-U2333-01 |
28 Jun 2021 |
N/A |
Valid |
|||
Discharge Licence |
WT00040069-2021 |
10/1/2022 |
31/1/2027 |
Valid |
|||
Construction Noise Permit |
N/A |
||||||
3.2.1.
A summary of the current status on submission under EP-555/2018/A is
shown in Table 3.2.
Table 3.2 Summary of
submission status under EP-555/2018/A
Submission |
Date
of Latest Submission^ or Approval# |
|
Condition 1.12 |
Notification of Commencement Date of
Works |
3 June 2021 ^ |
Condition 2.7 |
Submission of Management Organization
of Main Construction Companies, the ET and the IEC |
20 May 2021 ^ |
Condition 2.8 |
Submission of Construction Works
Schedule and Location Plan |
22 June 2021 # |
Condition 2.9 |
Submission of Breeding Bird Survey
Report |
29 December 2020 # |
Condition 3.3 |
Submission of Baseline Monitoring
Report |
24 June 2021 # |
Condition 4.2 |
Setting up Dedicated Internet Website |
28 April 2021 ^ |
3.3.1
Mitigation measures according to the environmental mitigation
implementation schedule and the EIA were generally implemented by the
Contractor as listed and shown in Appendix 3.1.
Noise Monitoring Stations
4.1.1.
The noise monitoring stations for the Project are listed and shown in Table
4.1 and Figure 4.1.
Table 4.1 Noise Monitoring Station
Remarks A:
As discussed with the lot owner, a fine adjustment of location at the
boundary of 1 Tung Wan Tau Road was proposed and approved in the Baseline
Monitoring Report, in order to prevent access obstruction.
Noise Monitoring
Parameters, Frequency and Duration
4.1.2.
For daytime construction work on normal weekdays (0700-1900 Monday to
Saturday), one set of 30-min measurement shall be carried out at each NMS every
week. Measurement procedures shall be referred to the Noise Control
Ordinance-TM. Construction noise level shall be measured in terms of the
A-weighted equivalent continuous sound pressure level (Leq). Leq
30min shall be used as the monitoring parameter. As supplementary information
for data auditing, statistical results such as L10 and L90
shall also be obtained for reference.
EVENT and action plan
4.1.3. Noise Standards for Daytime Construction Activities are
specified under EIAO-TM. The Action and Limit levels for construction noise are
defined in Table 4.3 and Appendix
4.1. Should non-compliance of the criteria occurs, action in
accordance with the Event and Action Plan in Appendix 6.1 shall be carried out.
Table 4.3 Action and
Limit Level for Noise Monitoring
Air Quality Monitoring
Stations
4.2.1.
The air monitoring stations for the Project are listed and shown in Table
4.4 and Figure 4.3.
Table 4.4 Air Monitoring
Station
Monitoring Station |
Location |
Level (in terms of no. of floor) |
AMS1 A |
Silvermine Beach Resort |
G/F |
AMS2 B, C |
1 Tung Wan Tau Road |
G/F |
Remarks A:
AMS1 recommended under EM&A manual is at the north of boundary wall
of Silvermine Beach Resort. Positioning of HVS on a narrow road at the northern
boundary wall would obstruct access of passengers. After liaison with the
resort owner, HVS is located near the eastern boundary wall, which is
representative and suitable for air quality monitoring. Thus, fine adjustment
of location at the boundary of Silvermine Beach Resort was therefore proposed
and approved in the Baseline Monitoring Report.
Remarks B: As discussed with the lot owner, a fine
adjustment of location at the boundary of 1 Tung Wan Tau Road was proposed and
approved in the Baseline Monitoring Report, in order to prevent access
obstruction and to minimize noise nuisance induced from HVS operation.
Remarks
C: As the agreement of ER and IEC, a
fine adjustment of location at the boundary of 1 Tung Wan Tau Road was proposed
and approved in the impact monitoring, in order to prevent the interruption of
GI working area conducted by contractor.
Air Monitoring Parameters,
Frequency and Duration
4.2.2.
One-hour and 24-hour TSP levels shall be measured to indicate the
impacts of construction dust on air quality.
4.2.3.
24-hour TSP shall be sampled at least once in every 6 days, while
sampling for 1-hour TSP shall be at least 3 times in every 6 days when the
highest dust impact takes place.
Wind Data
4.2.4.
Hong Kong Observatory (HKO) meteorological information is widely
accepted to be used in various environmental monitoring practices within HKSAR
due to its professional quality and precision. Therefore, the daily wind data
including Prevailing Wind Direction (degrees) and Mean Wind Speed (km/h) were
obtained from Peng Chau Automatic Weather Station to serve as the
representative data for meteorological condition during monitoring. The method
was agreed by the IEC and approved by the ER on 4 December 2020. The
representative wind data from Peng Chau Station were obtained covering the
1-hour and 24-hour TSP monitoring periods. The wind data were extracted and shown in Appendix 4.3.
EVENT and action plan
4.2.5.
The Action and Limit levels for construction air quality are defined in Table 4.6 and Appendix
4.1. Should non-compliance of the air
quality criteria occur, action in accordance with the Event and Action Plan in Appendix
6.1 shall
be carried out.
Table 4.6 Action and
Limit Level for Air Quality Monitoring
Parameter |
Monitoring
Station |
Action
Level (µg/m3) |
Limit
Level (µg/m3) |
24-hour TSP Level |
AMS1 |
176.0 |
260.0 |
AMS2 |
176.0 |
260.0 |
|
1-hour TSP Level |
AMS1 |
276.5 |
500.0 |
AMS2 |
283.7 |
500.0 |
WATER QUALITY MONITORING STATIONS
4.3.1.
Water quality monitoring shall be undertaken at 7 monitoring stations in
the reporting month. The proposed water quality monitoring stations of the
Project are shown in Table 4.7 and Figure 4.3.
Table 4.7 Marine Water Quality Stations for Water
Quality Monitoring
Station |
Description |
Monitoring Period |
Monitoring Station |
Easting |
Northing |
W1 |
Wang Tong River (Major
tributary) |
Mid-Flood |
Impact |
817747 |
814519 |
Mid-Ebb |
Control |
||||
W2 |
Wang Tong River (Major
tributary) |
Mid-Flood |
Impact |
817775 |
814471 |
Mid-Ebb |
Control |
||||
W3 * |
Wang Tong River (Minor tributary
to Tai Wai Yuen) |
Mid-Flood |
Impact |
817803 |
814537 |
Mid-Ebb |
Control |
||||
W4 |
Wang Tong River (Minor
tributary to Tai Wai Yuen) |
Mid-Flood |
Impact |
817825 |
814481 |
Mid-Ebb |
Control |
||||
W5 |
Silvermine Bay (Near
Silvermine Bay Beach) |
Mid-Flood |
Control |
817909 |
814452 |
Mid-Ebb |
Impact |
||||
W6 |
Silvermine Bay (Near
Silvermine Bay Beach) |
Mid-Flood |
Control |
818024 |
814447 |
Mid-Ebb |
Impact |
||||
W7 |
Silvermine Bay (Open Water) |
Mid-Flood |
Control |
818061 |
814277 |
Mid-Ebb |
Impact |
||||
W8 |
Silvermine Bay (Open Water) |
Mid-Flood |
Control |
818224 |
814444 |
Mid-Ebb |
Impact |
Remark *: Water quality monitoring at Station W3
was cancelled with verification from the IEC and approval from the EPD.
Water Quality Parameters,
Frequency and Duration
4.3.2.
The levels of dissolved oxygen (DO), turbidity, salinity and pH shall be
measured in situ while suspended solids (SS) is determined by laboratory
analysis at all the designated monitoring stations.
4.3.3.
In association with the water quality parameters, other relevant data
shall also be recorded, such as monitoring location / position, time, water
temperature, DO saturation, weather conditions, and any special phenomena
underway near the monitoring station.
4.3.4.
Impact Monitoring shall be carried out 3 days per week, at mid-flood and
mid-ebb tides (within ± 1.75 hour of the predicted time). The interval between
two sets of monitoring shall not be less than 36 hours. The monitoring period
should avoid concurrent marine project in the vicinity.
4.3.5.
The sampling frequency of at least three days per week should be
undertaken when the highest dust impact occurs. Upon completion of the
construction works, the monitoring exercise at the designated monitoring
locations should be continued for four weeks in the same manner as the impact
monitoring. In case exceedance of Action/Limit Level is recorded, the frequency
shall be increased as per the Event and Action Plan.
4.3.6.
To ensure the robustness of in-situ measurement, parameters shall be
measured in duplicate. In case the difference between duplicates is larger than
25%, a third set of measurement shall be carried out.
EVENT and action plan
4.3.7.
The Action and Limit levels for construction water quality are defined
in Table 4.9 and Appendix
4.1. Should the monitoring results of the water quality parameters at any
designated monitoring station exceed the water quality criteria, action in
accordance with the Event and Action Plan in Appendix
6.1 shall be carried out.
Table 4.9 Action and
Limit Level for Water Quality Monitoring
Monitoring Station |
Depth |
DO (mg/L) + |
Turbidity (NTU) ~ |
SS (mg/L) ~ |
|||
Action Level |
Limit Level |
Action Level |
Limit Level |
Action Level |
Limit Level |
||
W1 |
Surface,
Middle & Bottom |
6.5 |
5.3 |
7.7 NTU or
120% of upstream control station's turbidity at the same tide of the same day,
whichever is higher |
12.4 NTU or 130%
of upstream control station's turbidity at the same tide of the same day,
whichever is higher |
8.9 mg/L or 120% of
upstream control station's SS at the same tide of the same day, whichever is
higher |
11.3 mg/L or 130% of
upstream control station's SS at the same tide of the same day, whichever is
higher |
W2 |
|||||||
W4 |
|||||||
W5 |
Surface,
Middle & Bottom |
5.9 |
5.5 |
9.8 NTU or
120% of upstream control station's turbidity at the same tide of the same day,
whichever is higher |
10.5 NTU or 130%
of upstream control station's turbidity at the same tide of the same day,
whichever is higher |
12.6 mg/L or 120% of
upstream control station's SS at the same tide of the same day, whichever is
higher |
15.0 mg/L or 130% of
upstream control station's SS at the same tide of the same day, whichever is
higher |
W6 |
|||||||
W7 |
|||||||
W8 |
Surface &
Middle |
||||||
Bottom |
5.9 |
5.5 |
Remarks +: For DO, non-compliance occurs when
monitoring results is lower than the limits.
Remarks ~: For SS and Turbidity, non-compliance
occurs when monitoring results is larger than the limits
5.0.1
The environmental monitoring were implemented as per the environment
monitoring schedules for reporting period.
5.1.1
Noise monitoring results measured in this reporting period are reviewed
and summarized. Details of noise monitoring results and graphical presentation
can be referred in Appendix 5.2.
5.1.2
No action or limit level exceedance was recorded in this reporting
period.
5.2.1
Air quality monitoring results measured in this reporting period are
reviewed and summarized. Details of air
monitoring results and graphical presentation can be referred in Appendix 5.3.
5.2.2
No action or limit level exceedance was recorded in this reporting period.
5.3.1
Water quality
monitoring was conducted at seven monitoring stations three days per week in
the reporting period since 17th March. However, due to no marine-based construction works before 27th May 2022, water quality
monitoring results before 27th May 2022 were taken as reference such that no
action and limit level exceedance was concluded and recorded before the day.
Review of action or limit level exceedance was conducted for water quality
monitoring results after 27th May 2022 when marine-based construction work
commenced. Details of water quality monitoring
results and graphical presentation can be referred in Appendix 5.4.
5.4.1
The quantities of waste for disposal in the Reporting Period are
summarized in Table 5.1 and Table 5.2.
Table
5.1 Summary of Quantities of Inert C&D Materials
Waste Type |
Quantity (this period) |
Quantity (Project commencement to the end of the last
quarter) |
Cumulative
Quantity-to-Date |
Hard Rock and Large Broken Concrete (Inert) (in ‘000m3) |
0 |
0.007 |
0.007 |
Reused in this Contract (Inert) (in ‘000m3) |
0 |
0 |
0 |
Reused in other Projects (Inert) (in ‘000m3) |
0 |
0 |
0 |
Disposal as Public Fill (Inert) (in ‘000m3) |
0 |
0 |
0 |
Table 5.2 Summary
of Quantities of C&D Wastes
Waste Type |
Quantity (this quarter) |
Quantity (Project
commencement to the end of last quarter) |
Cumulative
Quantity-to-Date |
Metals (in ‘000kg) |
0 |
0 |
0 |
Paper / Cardboard Packing (in ‘000kg) |
0 |
0 |
0 |
Plastics (in ‘000kg) |
0 |
0.03 |
0.03 |
Chemical Wastes (in ‘000kg) |
0 |
0 |
0 |
General Refuses (in ‘000m3) |
0.01 |
0.026 |
0.036 |
6.2.1
No action or limit level exceedance was recorded in this reporting
period.
6.3.1
No action or limit level exceedance was recorded in this reporting
period.
6.4.1
The Event Action Plan for construction noise, air quality and water
quality are presented in Appendix
6.1.
6.4.2
The summary of exceedance is presented in Appendix 6.2.
6.5.1
During the reporting period, the Environmental Team (ET) conducted weekly site inspections and IEC attended
the joint site inspection monthly.
6.5.2 During this reporting month, monthly
landscape site audits were conducted monthly.
6.5.3
No non-compliance was found during the site
inspection while reminders on environmental measures were recommended.
6.6.1
No environmental non-compliance
was recorded in the reporting period.
6.7.1
There was no
particular action taken since no non-compliance was recorded in the reporting
period.
7.0.1.
No environmental
complaint, notification of summons and successful prosecution regarding
construction works was recorded in the reporting period.
7.0.2.
The details of cumulative complaint log and updated summary of
complaints are presented in Appendix 8.1.
7.0.3.
Cumulative statistic on complaints and successful prosecutions are
summarized in Table 8.1 and Table 8.2 respectively.
Table 8.1 Cumulative
Statistics on Complaints
Reporting
Period |
No.
of Complaints |
April
2022 – June 2022 |
0 |
Project
commencement to the end of last reporting month |
- |
Total |
0 |
Table 8.2 Cumulative
Statistics on Successful Prosecutions
Environmental
Parameters |
Cumulative
No. Brought Forward |
No.
of Successful Prosecutions this month (Offence Date) |
Cumulative
No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
8.0.1.
The EM&A programme was carried out in accordance with the EM&A
Manual requirements, minor alterations to the programme proposed were made in
response to changing circumstances.
8.0.2.
The EM&A programme was considered effective and no change is anticipated as reviewed
for this quarter.